Port Lincoln Hotel

Project Details: Due for completion September 2007, Cost $2m
Article from Adelaide Advertiser |
Project Description
The new Port Lincoln Hotel is a seven storey building, the Ground & First floors comprising of Lounge Bar, Bistro Café, Gaming Rooms, Function Areas & Meeting Rooms.
Levels 2 to 6 have 111 luxurious guest accommodation rooms.
Services Description
Ground & First floors have air cooled reverse cycle split ducted type air conditioning systems serving the occupied areas, including exhaust & outside air ducted systems. Levels 2 to 6 have air cooled split room air conditioning units comprising of above ceiling ducted evaporator section and remote air cooled condenser sets.
|
Palais Apartments
Project Description
This steel structured, 6 level building is located on North Terrace in the city. It incorporates 100 apartments, ground floor retails tenancies and a two level basement car park for the residents.
Services Description
The apartments are served reverse cycle, under ceiling mounted air conditioning units and a common, ducted fresh air system. The ground floor tenancies have split ducted a/c systems with multiple exhaust systems ventilating the 2 level car park.
Project Data: Completion due December 2006. Mechanical Services value approx $900k |

|
Stillwell Ford
Project Description
This is a major expansion and upgrade to the Adtrans Group's Medindie premises including a new car showroom and workshop facility.
Services Description
The showroom and offices are served by packaged and split ducted, reverse cycle air conditioning systems and ducted fresh air and exhausts. The new workshop is served by roof mounted evaporative coolers and ducted fume exhaust systems.
Project Data: Completion due July 2006. Mechanical Services value approx $500k
Domain Apartments
Project Description
New 6 level apartment block on Grenfell street in the city.
Services Description
Individual ducted split systems to each apartment. Heating water to serve pool and spa heat exchangers as well as pool air handler. Car park and exhaust systems with associated fans and ductwork.
Project Details: Completed Dec 05. Cost $800k |
 |
Reading Cinemas


|
Project Description
New cinema complex with under cover parking facility comprising of 7 cinemas, lounge bar and foyer candy bar. Located at the West Lakes Sopping Centre complex.
Services Description
Reverse cycle package and split ducted air conditioning systems. Ducted exhaust and smoke spill systems with Co2 monitoring in the cinema areas. All mechanical installations controlled by BMS monitoring system. Car park exhaust system incorporating Bus exchange ventilation system.
Project Details: Completed Aug 2004. Cost $850k
|
Mawson Lakes Hotel
Project Description
New hotel complex consisting of 24 accommodation rooms, Conference facility, Bars, Bistro's, Pokies Room, Bottle Shop and commercial kitchen.
Services Description
The accommodation rooms were served by individual wall mount split a/c units. Packaged and split ducted, reverse cycle a/c units serve the bars and bistro. The commercial kitchen is fitted with stainless steel exhaust canopy and make up air via an evaporative cooling system.
Project Details: Completed April 2004. Cost $520k
|
|
Gropep

Project Description
Extensions and renovations to the GroPep Production Facility at Thebarton S.A. This entailed fume hood installations, clean room pressurisation & conditioning systems with high level HEPA & NEPA filtration. GroPep is a biopharmaceutical company that develops, manufactures and commercialises products that bring significant benefit to human health.
Services Description
Reverse cycle ducted split air conditioning systems incorporating fan assisted HEPA filtration modules removing 99.97% of sub micron particles to the dispatch, dispensing suite & airlock areas. Ducted exhausts, fresh air systems, fume hoods and variable speed drives also form part of this critical environment conditioning. A computerized Building Management System controls the mechanical service plant.
Project Details: Completed 2004, Cost $590k
Air International

Project Description
Components manufacture company that supply's Holden's and Mitsubishi. Located at Elizabeth adjacent the Holden manufacturing plant
.
Services Description
Evaporative air conditioning, gas radiant heating and general exhaust systems were installed in the components manufacturing area. Office and administration areas are conditioned by reverse cycle split ducted air conditioning systems with general exhaust systems installed in toilets and change rooms.
AAMI Stadium Northern Grandstand
Project Description
New Northern grandstand at football park – West lakes. This incorporated Corporate boxes, Kiosks and bars, Kitchen and Bistro dining areas and many toilet areas.
Services Description
Reverse cycle packaged and wall split style air conditioning systems. Evaporative air conditioning and Kitchen canopies, Ducted exhaust and fresh air systems. Computerised Building Management System (BMS) control the operation of the systems.
Innovation House
Project Description
New office building located at Mawson lakes with training and seminar rooms and a cafeteria.
Services Description
Reverse cycle split ducted and ceiling cassette style air conditioning systems. Ducted exhaust and fresh air systems. Computerised Building Management System (BMS) control the operation of the systems.
Carlson Country Inn & Suites Project Description
Formally the Beneficial Finance building the project included the redevelopment of an eight story heritage office building into a four star hotel complex. With 76 guest rooms ranging from standard accommodation to suites the project also included kitchen and restaurant, reception, swimming pool, gymnasium and conference facilities.
Services Description
Variable Refrigerant Volume (VRV) air conditioning system incorporating a roof top plant area housing the out door units. Individual fan coils for each suite and specialist area. Refrigeration runs up to 50 meters in length with 30 meter lifts. Various exhaust and fresh air systems.
Phoenix Society

Project Description
This project included the construction of a controlled environment printing facility built from ‘Bondor' sandwich paneling within the existing saw tooth structure and included modifications to the existing heating and cooling serving the general factory areas.
Services Description
Westside was engaged on a design and construct basis for the controlled environment air conditioning serving the new printing facility. The system included the use of split ducted a/c units providing comfort conditions for each of the printing areas. Fresh air intake and special ducted exhaust systems were provided matching pressure requirements of each area.
Tarac Distillers - Barossa Valley
Project Description
Tarac Distillers Pty. Ltd. have built a new distilling and bottling facility outside of Angaston in South Australia's Barossa Valley. This particular project incorporated the construction of a large warehouse building to house their distilling plant and associated distribution systems.
Services Description
Westside was provided with a client design brief and engaged to design and construct a specialist exhaust system serving the distilling process plant. Air extraction points were located to suit the distilling process system of equipment and conveyer belts. Due to the aggressive nature of the discharge all ducting was coated internally with a two part epoxy system.
|